"Construction of the New Headquarters of the University Hospital of the Jagiellonian University Medical Center Cracow Prokocim". Execution of external networks and underfloor sewerage in buildings.
Scope of the underfloor sewage system: 610 rm
Scope of external networks:
Sanitary sewage system – 1,597 rm
Dirty and clean rainwater drainage system - 3 590 rm + 1 018 rm
Infectious sewerage system – 456 rm
Domestic water system – 492 rm
Fire protection water system – 1,285 rm
Internal low-pressure gas network – 243 rm
Heating connection – 910 rm
Water supply connection Dn600 – 29 rm
Secondary connection Dn300 – 426 rm
|